A journal of the Reconstruction process of my house in Thomson.

This blogs serves as a journal to record the reconstruction process of a brand new house in Singapore

Sunday, November 14, 2010


Posted by Picasa

Teka Hx720. I just bought this oven together with some other hob and hood. I am likely to change to an island hood though.
Will update other appliances pictures soon
Posted by Picasa

on the 2nd floor slab


The 2nd floor slab facing the front


The RC staircase


This will be my future masterbed room view
Posted by Picasa


Concreting work done on 2nd floor slab


Concrete truck parked behind the pump truck
Posted by Picasa

Friday, November 12, 2010

Removal of 2nd floor formwork with concrete staircase

Tomorrow is the removal of 2nd floor formwork. I am so excited. The 2nd floor concrete slab will be ready together with a RC staircase to the 3rd storey. Once the formworks have been removed, we can move in the 1st floor steel 'fishbone' staircase and start constructing the 3rd storey!

my lady boss
Posted by Picasa

I am the temporary site supervisor


Doing up the 2nd floor


Once the formwork has been removed, there are lot of space
Posted by Picasa

After the formworks have been removed, the 1st floor concrete slab is completed. Now moving on to do the 2nd storey slab


This is how the 1st floor slab looks like. Floor to ceiling 3375mm
Posted by Picasa


Doing up the formwork for 1st floor slab


Once formwork is done, we can pour in the concrete
Posted by Picasa